Beginning on or around Wednesday, March 19, crews will begin lane closures on U.S. 50 in Vincennes near Fort Knox Drive.
These lane closures will occur in both the east and west bound passing lanes of U.S. 50.
Lane closures will allow for temporary crossover construction.
Crossover construction is expected to take a month to complete, depending on the weather.
Crossover construction is the first phase of a three phase bridge construction project over Fort Knox Drive.